Shanghai Hehui Optoelectronics

The 6th generation AMOLED display project of Hehui Optoelectronics Phase II, with a total investment of 27.278 billion yuan, was started on December 9, 2016. The total construction area of the main plant built by the project is about 390,000 square meters, of which the clean plant area is about 320,000 square meters, which is the largest purification plant in Shanghai's history. After reaching the standard, the production capacity is 30,000 glass substrates per month, and the products are 1 to 15 inches of display screens and modules, taking into account the flexible and hard board production technology.


The completion of the sixth-generation AMOLED production line will effectively improve the production capacity, product type and technical level of Huiguang. At the same time, it will further enhance the technical level of Shanghai's new display industry cluster, which is of great significance for promoting the development of new display industries in the future.